Completed Week Ending May 21st, 2006

NG30 Bulkheads Cut Out

MKNG-6 Outside Layup Installed

NG30 Inside Layup Installed

MKNG-6 Double Fabricated

NG51 Hardpoints Ready For Cutting

NG51 Hardpoints Cut Out

NG30 Hardpoints Installed

NG30 Outside Glassed
   

Completed Week Ending July 2nd, 2006

MKNG-6 Inside Layup Being Glassed

NG30 Initial Assembly
     

Completed Week Ending August 20th, 2006

Nose Strut Floxed In

NG 3 & 4 Floxed In

Nose Gear Bulkheads Being Glassed

F0 Bulkhead Being Attached

NG31 & 32 Being Floxed In